Start Project from Blueprint with New Gantt Chart by default
Hi Wrike, We have plently of projects that are created from the standard blueprint. The blueprint is set with "New Gantt Chart" view, however the users must always activate manually "New Gantt Chart" view when they're creating the project X from the Request Form (blueprint). Can we enable by default the "New Gantt Chart"…
-
New Gantt Chart - Enable "Start Constraint"
Hi Wrike, Every time I need to change the "Start Constraint" in the New Gantt chart, I don't have it, I must switch to the Old version Gantt Chart, click on the wheel, enable it and then and remove it from the list. Possible to fix it and add it to the New Gantt Chart ? Thank you.
-
Item deletion safeguards
Hello! I would like to suggest the addition of a deletion safeguard when it comes to deleting an item via right-click. At the moment, right-click > Delete from either Table or Gantt Chart views immediately deletes the item; no confirmation pop-up or box (like we have when we send a comment without an @mention). On the…
-
[Webinar] Kick-Start 2026: Master Gantt Charts in Wrike ✔️
TL;DR: Join our live webinar on March 20, 2026 at 9:00 AM PST to learn how to use Wrike’s Gantt Charts to visualize timelines, track dependencies, and keep projects on schedule. Hello folks 👋🏼 We’re excited to invite you to our next live webinar, focused on using Wrike’s Gantt Charts to plan, adjust, and monitor your…
-
Export to PDF feature for the New Gantt Chart
The New Gantt Chart is missing the export to PDF feature, which is available in the classic Gantt Chart. Can this please be added to the New Gantt Chart? Executives are not interested in the task details for each project, which is what you get when exporting to Excel in the New Gantt Chart. They only want to see a…
-
Project tracking metrics
Hi Wrike, Can you please make some additional task metrics available, particularly in gantt view, such as total slack (for each task), latest start (before becoming critical path), and latest finish? For detailed project managers, these metrics really help to identify where effort should be placed to keep the whole thing…
-
How to create Views via the API?
We'd like to setup separate client facing and internal views (Gantt charts) for Projects. We're going to be creating a separate project for each client, and would like to programatically create the client facing and internal views with default filters configured. What are the best ways to accomplish this?
-
Gantt Chart - Running Total
I am probably approaching this wrong. My leadership has asked for a Gantt chart, with a chart showing invoices and billings along with project milestones with a running total column so they can forecast both budget and workflow from one screen. I am not finding a way to do this. Open to suggestions