How does one add a lead or a lag to a dependency.
For instance, I have a SS dependency between task 1 (painting the cabinets) and task 2 (sealing the cabinets). Task 2 can start when task 1 starts, but two hours must elapse from the time the first cabinet is painted until the sealer can be applied (I have two people working, so it's not necessary to complete the painting of the cabinets before the sealer can start going on the ones that are dry).
So for task 2 it would look something like this for the dependency: 1SS+2h
How is this done in Wrike??