There is an amazing feature in the date field of request forms that allows you to "allow only dates to be selected that are: "blank" days after the form is submitted or later.
I can't find any way to limit this to business days. I'm using this form for people to request creative deliverables from our creative team, and I need to delay the review date by 5 business days from the request date, since we don't work on weekends. However, this 5 days includes weekends, and if a task is requested and a weekend falls in that time span, it's counted, giving us 3 days.
I've gone and checked and I have our work schedule set globally to M-F. Is there somewhere else that I can completely exclude weekends globally so that this form feature will work?