Hi,
As a project manager I am task with monitoring who has the bandwidth to take on more projects. The current structure of the tool allows me to create reports by project or by task. This system doesn't a full picture of anyone's work for a given week.
For example the project report can tell me that an analyst on my team has 30 hours of work for the week which tells me they have room to take on about another 10-15 hours of work. The task report shows that same member with 20 hours of work as an assignee and not a project owner. So technically this analyst has 50 hours of work in a 40 hour work week which means she is over 10 hours but unless I look at both reports I wont know that.
Is there a way to capture project owners and assignee's to a task in the same report?