Scenario: I have a large program with many folders/projects and sub folders/projects. I want to be able to see, on the gantt view, all tasks in the program assigned to me (or another single user), without seeing any folders/projects that do not contain any tasks assigned to me (or them).
The above used to be possible by using the "hide empty folders" button after filtering on tasks assigned to me.
Now that "filtering by project information" has been introduced on the gantt view, when I try the above scenario, the "hide empty folders" button no longer hides folders that have no tasks assigned to me. this means that I see hundreds of project/folders that have nothing to do with me.
I can't use the project filter for projects assigned to me because some of my tasks appear in projects I don't own. I can't filter on projects between certain dates because some of my tasks are not in project, just folders.
Is there anyway around this, or can the "hide empty folders" be made to behave like it used to?