We have a blueprint project set up to span a 5 week timeframe. There are 5 tasks in the blueprint, each set up with start and end dates.
Sometimes a project will come in that takes less time than the 5 weeks built into the blueprint. What do I need to do so that after I launch the blueprint then I shorten the project timeframe all the tasks within the project re-align accordingly?
I have attempted to use the date-rollup feature, it does not work at all. I have created the blueprint with all 5 tasks being subtasks, does not re-align properly. I have made the final task a milestone and changed that date to be shorter than the blueprint timeframe, hit Apply when prompted to re-align all the subtask due dates - nothing happened. I've also tested the blueprint with and without the tasks being dependent. Nothing is working to re-align the dates correctly if I need to shorten the project timeframe.
I do not want to have to tell my team to manually adjust each tasks date range.