So we recently had someone leave the company and I was going through to put all of those project in a cancelled status. A few things on this...
1. If you cancel a project at the "cancellation" does not trickle down to the sub projects or tasks.
2. If you drag the whole thing into Archive, there is no status change (shouldn't archive mean that the status changes to something along the line of archived??)
3. Even if you do go through the exercise of moving to archive and manually cancelling ALL tasks, the hours still show up in your workload view!! I'm not sure how that is a function but that seems silly to me. They don't show up as a task but the hour allocation remains. This is something that should be fixed ASAP in my opinion. It gives a terrible view into peoples bandwidth if there are many tasks that were cancelled but the hours are still allocated to that task.