Hello,
When populating a start and finish date in Wrike, if the date range is wider than 3 years apart it does not generate dates?
Do you have a solution for this?
Hi @Marcus Clarke 👋 thanks for creating and sharing this post.
At the moment, tasks have a maximum duration limit of 1095 days (3 years). Because of this, request forms aren't able to populate date ranges that go beyond that 3-year mark.
As a workaround, you can use a project-type item instead of a task for long-running work. Alternatively, you can map the dates to both the form fields and the description field so you have a record of them, and then manually adjust the project dates after the form is submitted.
I know this isn’t the most ideal solution, but I’ve gone ahead and shared your feedback with our product team. I'll be sure to keep you posted right here if we have any updates on this 👍