Different projects have different scheduling considerations. Some projects within the company have work that gets completed over the weekend and some projects work on a Mon-Fri schedule. It is tricky that I have to set this selections (work week vs calendar week) at the account level. Ultimately half of my team is going to be un-happy regardless what choice I make. I would love for the flexibility to be able to set this at either the folder or project level so that the calendar can best suit the needs of the project. Thanks.