For the most part, we really appreciate the work schedule feature in Wrike. Users will add their vacation time, and project timelines are automatically adjusted. The majority of our projects don't have hard deadlines, so it's OK for them to be pushed out a few days.
We do however, have some projects that have strict launch dates that cannot be moved. Is there some way around the work schedule feature from pushing these specific project timelines out when a user adds vacation time to work schedule?
I'm aware of the wrike labs "Disable automatic task rescheduling" option, however I have not enabled it because as mentioned above, the majority of projects this feature is super helpful for.
I've searched the community for workarounds and am not finding anything recent, much of the conversations around work schedules happened several years ago.