We're starting to use booked effort to reserve employee time for projects that are specced only at a high level at this point.
My question is, what's the usual process to "convert" booked effort to task effort?
Say we have a project that we know is going to take about 100hours to deliver. I have booked two people to the project at 50 hours each and this is appearing in their workload plans. All good.
At some point in the future we write the detailed proposal for the project which contains a list of all the individual tasks and their dates and times. I assign the two people that were booked to the project to these tasks and now their workload plan is showing them as over resourced. Do I simply delete the booked effort or is there a more intelligent way of consuming the booked time and transforming it into task time? Am I overthinking this?