When we select Predecessor info to be displayed on the table/Gantt view of a specific project, the information actually shown in the Predecessor column is both predecessor and successor task IDs separated by a comma if there are multiple dependencies. Trying to follow the dependency lines from task to task in a complex Gantt is not efficient.
To confirm which is which, user has to go into the specific task and select "dependencies" where it actually shows all Predecessor and Successor tasks.
For efficiency, recommend that the user is able to select either/both Predecessor and Successor which would show up in separate columns in the table/Gantt view, therefore allowing the user to see this info without having to go into each task separately to confirm.